The sections' assembly started at workshops of the shipyard
Works over shipbuilding orders of the company Ulstein entered stage of sections' assembly. According to the information of head of production department on Zaliv Mr. Valentin Pikhterev, hull's treatment workshop already have completed cutting of 900 tons of steel for the first order in the series, all the steel is ransferred to the assembly-welding production and the workers have commenced manufacturing of units, subsections and sections.
Up to March 1, the readiness of hull Yno. 291 already makes up 12,9%, within the month time Zaliv scheduled manufacturing of 50% of all the works necessary for this project.
Simultaneously with execution of this order, the works over the assembly of nine sections for the next vessel continues. It is expected, that until the end of March this year, readiness of the hull under construction for the vessel of seismic reconnaissance will make up more than 15%.
It is worth additional notice that construction of some sections include works over stainless steel that requires special skills and high qualification of welders subject to additional certification.
Добавлено: 03-03-2011 (отредактировано: 23-11-2011 в 14:19)